This Concrete project took place in the Oakland (Hill's) Ca. We will be pouring over 25 yards of concrete
We are starting to frame for the stairs and raise the two raise patio's we imported over 25 yards of base rock.
Finishing pouring concrete for raise stamp patio. Also add concrete stairs so that the customer can up and down all the way around
Removing hot tub and shed to make room for raise stamp concrete patio.
Starting to fill in dirt for raise stamp concrete patio. We use approximate 6 yards of dirt. Along with 5-6 yards of base to get our final level.
First raise stamp concrete patio is complete.
Other side of patio. We added another raise concrete patio with low voltage lights.
Starting to bring in Base rock in approximate 7 yards for this side.
Raise stamp concrete patio is complete with wheelchair access and low voltage light.
Remove old wood stairs and starting to frame for new ones